Safety works at Etherow Country Park reservoir in Compstall are forecast to cost £3.5 million, with £1.86 million found. The bridge is due to reopen in spring.
The cost of safety repairs at the reservoir in Etherow Country Park, Compstall, has risen to a forecast £3.5 million. The council first set aside £450,000 for the work. It has found £1.86 million so far, leaving a shortfall of £1.64 million.
The figures are in an update on the Etherow Reservoir Repairs project for the Communities and Transport Scrutiny Committee, which meets tonight, Monday 23 November. The covering report asks the Cabinet on 8 December to let officers finish the project within the £3.5 million total.
Overview
- Forecast total cost: £3.5 million
- Spent by 21 October 2026: £1,718,000
- Money found so far: £1.86 million, leaving a £1.64 million gap
- Martin Clough Bridge: closure was expected from early October 2026, reopening in spring 2027
- Paddle House works: due to finish in spring 2027
Why the repairs are needed
Etherow Country Park Reservoir is a Category A high-risk reservoir under the Reservoirs Act 1975. That category means an uncontrolled release of water could endanger life. It does not mean failure is likely: the update says the Environment Agency’s flood maps “do not indicate the structural condition of the reservoir or the likelihood of a failure occurring”.
The council is legally responsible for the reservoir’s safety. An independent engineer’s inspection in June 2023 listed safety measures that had to be investigated and carried out.
Why the cost has grown
As investigators looked closer, they found more problems than expected, especially at Martin Clough Bridge and the embankment beside it. Monitoring found “continuing movement within the structure”. The council has put a 3-tonne weight limit on the bridge until permanent repairs are done.
The work now covers:
- the Paddle House and other reservoir infrastructure
- Martin Clough Bridge, the road over it and the embankment
- an upgraded track through Ernocroft Wood, so residents and emergency services can still get in while the bridge is closed
- continued monitoring, traffic and access controls
The project was first put in the council’s capital programme in 2024/25 with £450,000 over three years. A 2024 procurement document put the likely contract value at about £850,000.
The council’s funding position, as the covering report sets it out:
| Amount | |
|---|---|
| Spent to 21 October 2026 | £1,718,000 |
| Revised total forecast | £3,500,000 |
| Funding found so far | £1,860,000 |
| Shortfall | £1,640,000 |
| Possible contribution from the 2027/28 capital programme | £150,000 |
| Still to find | £1,490,000 |
The report says no spending beyond the approved total will be committed without further approval. It is also tightening how the contract is run, including dedicated quantity surveying and a lessons-learned review at the end.
What it means for you
Work started on site in August 2026. The update’s timetable for the next phases is:
| Phase | Timing in the update |
|---|---|
| Paddle House and reservoir infrastructure | Now under way, finishing in spring 2027 |
| Alternative access through Ernocroft Wood | Upgraded and available during the bridge closure |
| Martin Clough Bridge, road and embankment | Closure “expected early Oct 26”, reopening in spring 2027 |
| Whole project | Expected to finish in spring 2027 |
The council says all dates depend on design, approvals and conditions on site. We could not confirm from the council’s website today whether the bridge closure has started. Its Etherow Country Park page, last updated in June, does not mention it.