More than 300 buildings in Stockport town centre could be required to connect to a heat network. A six-week consultation is planned from mid-December.

More than 300 buildings in and around Stockport town centre could one day be required to connect to a shared low-carbon heating network. The council plans a six-week public consultation on where the heat network zone should run, from mid-December 2026 to the end of January 2027.

The plan is in a report to the council’s Housing, Economy and Environment Scrutiny Committee, which meets on Thursday 26 November. Cabinet is asked to agree the consultation on Tuesday 8 December.

Overview

  • What: a heat network zone, an area where a shared heat network is expected to be the cheapest low-carbon heating
  • Where: mainly Stockport town centre
  • Who could be affected: a provisional list of over 300 buildings belonging to 93 owners
  • Consultation: six weeks, mid-December 2026 to the end of January 2027, if Cabinet agrees on 8 December
  • What is asked: views on the zone boundary, not on whether a heat network is built

What a heat network is

A heat network carries heat through insulated pipes underground from a central source to many buildings. It means each building does not need its own boiler, the report says. Customers can include public buildings, shops, offices, hospitals, schools and homes.

The government created heat network zones in the Energy Act 2023. Stockport is in its Advanced Zoning Programme, which the report says lets it consult before the national regulations are laid before Parliament.

Who could be required to connect

The consultation plan lists a provisional long list of over 300 buildings in the current boundary, belonging to 93 owners. It describes them as buildings “potentially required to connect”.

Separately, it names 29 buildings for direct talks, including Stepping Hill Hospital, education and health buildings, commercial premises, logistics hubs and developers.

A Zone Coordinator will decide whether and when eligible buildings must join, following national rules. It will also handle exemptions, enforcement and penalties, the report says. Until one is appointed, the council is filling the role with the Greater Manchester Combined Authority.

How the zone was drawn

The proposed boundary comes from a national government energy model. It weighs how much heat buildings use against the heat sources nearby. Early talks with local partners have since refined it. United Utilities is listed as a possible heat source.

Who will be asked

The plan says anyone living, working or running a business in the zone can take part. It lists groups including:

  • the borough’s 63 councillors, the Mayor of Greater Manchester and three MPs
  • building owners, landlords and tenants in the zone
  • utility firms, including SP Electricity North West, Cadent and United Utilities
  • transport bodies, including TfGM, Network Rail and National Highways
  • Historic England, the Environment Agency and the Canal and River Trust
  • business groups, including Totally Stockport and the Federation of Small Businesses

The consultation is paid for from a government grant, with £40,000 set aside for staff time, venues, printing and postage.

What it means for you

Nothing changes yet. If you own, rent or run a building in the town centre, the consultation is your chance to say whether it should be inside the zone. The consultation plan points to an interactive map of the proposed boundary. Both meetings are open to the public, and the papers are on the council’s meetings website.